GeM transaction charges and the Annual Milestone Charge

GeM transaction charges are paid by sellers on orders they win, never for registering or bidding. Since 26 August 2025 they work in two layers. First, once a seller's orders in a financial year reach ₹20 lakh, it pays a one-time Annual Milestone Charge of ₹10,000 plus tax. Second, after that threshold, each order over ₹10 lakh carries a transaction charge of 0.30% of its value, with a flat ₹3 lakh for orders of ₹10 crore or more.

Everything on this subject comes from GeM's Revenue Policy, version 1.6, dated and effective 26 August 2025. It applies to bids with a bid opening date on or after 26 August 2025, and to direct purchase and L1 orders placed on or after that date. Earlier bids stay under version 1.5, in force from 9 August 2024.

The 2025 policy in one table

GeM seller charges under Revenue Policy v1.6
Charge Amount, excluding GST When it applies
Annual Milestone Charge₹10,000Once a financial year, when your orders reach ₹20 lakh
Transaction charge, order up to ₹10 lakhNilAlways
Transaction charge, order over ₹10 lakh and under ₹10 crore0.30% of order valueOnly after the ₹20 lakh threshold
Transaction charge, order of ₹10 crore or moreFlat ₹3,00,000Only after the ₹20 lakh threshold
Orders awarded before the ₹20 lakh thresholdNilAlways

GST is added to every charge. The PIB release of 28 October 2026 says nearly 97% of orders on GeM attract no transaction charge.

Annual Milestone Charge: the ₹20 lakh threshold

The policy measures your business by Seller Merchandise Value (SMV): the running total of the values of orders placed with you during the financial year, counted from the date each order or contract is placed. Each financial year is a separate unit, so SMV starts again from zero every 1 April.

When your SMV reaches ₹20 lakh, GeM levies the Annual Milestone Charge (AMC) of ₹10,000 plus applicable taxes. It is recovered at the moment you cross the threshold, and only once in that financial year.

Exempt orders still count. Orders that carry no transaction charge, such as government-to-government orders or contracts on nomination, are still added to your SMV and can trigger the AMC.

A seller whose orders total less than ₹20 lakh in a year pays nothing at all to GeM for that year.

Transaction charge slabs

Once the threshold is crossed, each new order is charged by its own value:

  • Up to ₹10 lakh: nil.
  • Over ₹10 lakh and under ₹10 crore: 0.30% of the order value. A ₹50 lakh order carries ₹15,000.
  • ₹10 crore or more: a flat fee of ₹3,00,000. The 0.30% rate would give ₹3 lakh at exactly ₹10 crore, so the flat fee works as a cap.

The order that takes you across ₹20 lakh is the one on which the AMC falls due. The policy says the transaction charge becomes payable "along with" the AMC on award, so that order is also charged by its slab. The calculator applies this reading.

Charges calculator

Enter the value of the new order, and the total value of orders already placed with you in the current financial year, then choose the order type: a normal order, or an exempt order placed by a government buyer on a restricted government-to-government bid, on nomination, or on single tender enquiry. The calculator returns the Annual Milestone Charge, if this order triggers it, the transaction charge and the total to pay, all excluding GST, with the rule applied. Amounts can be typed as ₹15,00,000, 15 lakh or 1.5 crore.

Forward auction and rate contract orders have their own rule of 0.30% capped at ₹3 lakh, and are not part of the calculator. A second calculator gives the vendor assessment fee for your turnover under the Vendor Validation Policy v5.0.

Charges on one order

Amounts, counts and yes or no answers only. No GeM ID, PAN, GSTIN, bank detail or login is asked for, and nothing is sent.

For example 15,00,000 or 15 lakh

Type 0 if this is your first order since 1 April

Vendor assessment fee

Amounts, counts and yes or no answers only. No GeM ID, PAN, GSTIN, bank detail or login is asked for, and nothing is sent.

For example 80 lakh or 1.5 crore

Worked examples

Charges on one order, by your earlier orders in the same financial year
Order value Earlier orders this year You pay, plus GST
₹8 lakhNilNothing; your total is still under ₹20 lakh
₹15 lakhNilNothing; your total reaches ₹15 lakh
₹15 lakh₹12 lakh₹14,500: AMC of ₹10,000 plus 0.30% of ₹15 lakh
₹8 lakh₹25 lakhNothing; orders up to ₹10 lakh are free
₹15 lakh₹25 lakh₹4,500: 0.30% of ₹15 lakh
₹50 lakh₹30 lakh₹15,000: 0.30% of ₹50 lakh
₹12 crore₹1 crore₹3,00,000 flat fee

In the fourth example, the ₹8 lakh order takes the total from ₹25 lakh to ₹33 lakh, but the AMC was already charged when the total first reached ₹20 lakh.

When and how to pay: 5 and 15 days

You become liable for the charges when the buyer awards you the contract on GeM.

  1. Invoice within 5 days. Generate the invoice for the transaction charge and AMC within 5 days of award, choosing the relevant GSTN. If you do not, GeM generates it automatically on your default GSTN.
  2. Pay by the earliest of three dates: within 15 days of award; before you raise your first invoice to the buyer on GeM; or on or before the due date of the first delivery under the contract.

If you miss the deadline, GeM acts under its Incident Management Policy V14.10, and your account resumes only after the pending charges are paid. Under that policy, non-payment leads to a temporary moratorium on the account. A moratorium blocks new bids and offers, though ongoing contracts can still be completed and paid.

Exemptions: government-to-government, nomination, single tender

Orders exempt from transaction charges
Case Condition
Government seller to government buyerOnly if the bid was restricted to government sellers, there was no bidding, or the contract was on nomination
Contract on nomination basisAny seller, government or private, if the buyer is a government buyer
Single tender enquiryAny seller, if the buyer is a government buyer
Administered price contractsExemption to take effect from a date GeM will notify

If private firms were allowed to bid alongside government sellers, the government-to-government exemption does not apply. The policy defines government buyers and sellers widely: central and state governments, union territories, central and state PSUs, autonomous and statutory bodies, constitutional and judicial bodies, government-owned SPVs and Section 8 companies, public sector banks and insurers, and joint ventures with at least 50% shareholding by such entities.

Exempt orders still count towards your SMV and the AMC.

Refunds when a buyer terminates

You can claim a refund of transaction charges only if the buyer terminates, partly closes or amends the contract within 6 months of award, for one of four reasons:

  1. The buyer selected the wrong goods or services.
  2. The buyer placed the order by mistake.
  3. The product or service was not required, or only partly required, so the buyer refused all or part of the quantity or stopped the service.
  4. The consignee was not available to receive the product or service.

Claim within 90 days of termination. For partial refusal, the refund is pro rata. No refund is given if the buyer terminated because you failed to meet your obligations or gave false or misleading information. GeM deducts any admissible amounts and your pending dues before refunding.

Forward auction, rate contract and Business Cockpit charges

Other GeM charges under Revenue Policy v1.6
Charge Amount, excluding GST Who pays
Forward auction order under ₹20,000NilNobody
Forward auction order of ₹20,000 or more0.30% of order value, maximum ₹3,00,000The forward auction buyer
Rate contract order, any value0.30% of order value, maximum ₹3,00,000The seller
Business Cockpit for OEMs₹6,00,000 a yearOEMs who subscribe

Business Cockpit is an optional analytics service that gives OEMs category data, detailed order information and CSV export. Disputes over unpaid charges fall under the exclusive jurisdiction of courts at New Delhi.

How the charges changed: 2024 and 2025

GeM transaction charges since 2024
Period Free orders Larger orders
Until 8 August 2024Up to ₹5 lakhPercentage charge, capped at ₹72.5 lakh
9 August 2024 to 25 August 2025, v1.5Up to ₹10 lakh0.30% up to ₹10 crore; flat ₹3 lakh over ₹10 crore
From 26 August 2025, v1.6Up to ₹10 lakh, and all orders before ₹20 lakh SMV0.30% under ₹10 crore; flat ₹3 lakh at ₹10 crore or more; plus ₹10,000 AMC

The 2024 change was announced in the PIB release of 21 September 2024, which describes the flat ₹3 lakh fee as "a massive reduction" from the earlier cap of ₹72.5 lakh. Version 1.6 added the Annual Milestone Charge and freed sellers from any transaction charge until they reach ₹20 lakh in the year.

Caution money: discontinued

Caution money was a separate, refundable deposit, not a charge. GeM's caution money notice says the requirement has been discontinued for sellers and service providers, and the PIB release of 28 October 2026 dates this to July 2025. Earlier deposits of ₹2,000, ₹10,000 or ₹25,000 can be withdrawn from Dashboard, Manage Caution Money Account, then Recalculate Threshold and Withdraw Excess Funds. The refund goes only to a verified bank account.

Frequently asked questions

What are GeM transaction charges in 2026?

Nil for orders up to ₹10 lakh and for all orders before your yearly total reaches ₹20 lakh. After that, 0.30% for orders over ₹10 lakh and under ₹10 crore, and a flat ₹3 lakh at ₹10 crore or more, plus GST.

What is the Annual Milestone Charge on GeM?

A one-time charge of ₹10,000 plus tax each financial year, levied when your total orders for the year reach ₹20 lakh.

When must I pay GeM transaction charges?

By the earliest of 15 days from award, your first invoice to the buyer, or the first delivery due date.

Is GST charged on GeM transaction charges?

Yes. All charges are exclusive of GST, which is added.

Who pays the forward auction charge?

The forward auction buyer, at 0.30% for orders of ₹20,000 or more, up to ₹3 lakh.

Can I get transaction charges refunded?

Only if the buyer terminates or reduces the contract within 6 months of award for one of four listed reasons, and you claim within 90 days.

Is there a registration fee on GeM?

No. Registration is free. Charges apply only to orders you win.