GeM payment timeline: from delivery to money in your account

GeM payment rules give sellers two firm clocks. The buyer has 10 days from receipt to inspect and accept or reject goods, and once it issues the acceptance certificate, it has 10 days to pay 100% of the bill. Both come from GeM's General Terms and Conditions, version 1.29. Where the buyer pays through PFMS, GeM's PFMS payment guide, last updated on 25 September 2025, adds penal interest of 1% a month for any delay beyond the 10 days.

The timeline at a glance

  1. Delivery. You deliver to the consignee named in the contract, within the delivery period.
  2. PRC. The consignee issues a Provisional Receipt Certificate online immediately after receiving the goods. The PRC date is the date of receipt.
  3. Inspection, up to 10 days. The buyer or consignee inspects and accepts or rejects within 10 days of receipt, unless the product terms (STC) or additional terms (ATC) set a different period.
  4. CRAC. On acceptance, part acceptance or rejection, the consignee issues the Consignee Receipt cum Acceptance Certificate. It is the basis for payment.
  5. Bill. You submit your invoice online; the buyer drafts the bill from the CRAC.
  6. Payment, within 10 days. 100% of the bill is paid within 10 days of the CRAC and online bill submission.
  7. Interest, for PFMS buyers. If payment is late, the buyer organisation owes penal interest of 1% a month, pro rata for the days of delay.

PRC: provisional receipt

The PRC records that goods have arrived, not that they are acceptable. Its date matters because the 10-day inspection window runs from it. Check your dashboard after each delivery: the GTC makes buyers and sellers responsible for keeping up with all dashboard notifications, including auto PRC and auto CRAC events.

If the consignee does not issue the PRC, follow up with the buyer first, then raise a ticket with GeM with the order number and proof of delivery.

Inspection and the 10-day acceptance window

Under clause 11 of the GTC, the buyer or consignee may inspect goods at its own cost, itself or through an appointed agency, and accept or reject any consignment "on proper justification" within 10 days of receipt, unless the STC or ATC say otherwise.

If goods are rejected:

  • No payment is made for rejected goods or services.
  • You must remove the rejected goods within 10 days of being told, at no cost to the buyer. After that, ground rent or warehousing charges can be charged to you.
  • If you still do not collect them within a reasonable time, the buyer can dispose of them at your risk and cost.

During the warranty period, the buyer can also call on you to rectify or replace defective goods within 7 days.

CRAC and SDAC

Acceptance certificates on GeM
Certificate Issued by What it does
PRC, Provisional Receipt CertificateConsignee, online, on receipt of goodsFixes the date of receipt
CRAC, Consignee Receipt cum Acceptance CertificateConsignee, after inspectionRecords acceptance, part acceptance or rejection; basis of payment for goods
SDAC, Service Delivery Acceptance CertificateBuyer organisation, for servicesBasis of payment for services

For services, the buyer can reject within 10 days of receipt of the service, in line with the service level agreement. The date of receipt is the date of your online invoice for the service period or the date the service was completed, whichever is later.

Bill and payment within 10 days

Clause 12 of the GTC sets the payment terms:

  • Goods: 100% payment within 10 days of the CRAC and online submission of bills, unless the STC or ATC say otherwise.
  • Services: 100% of monthly bills, unless otherwise specified, within 10 days of the SDAC and online submission of bills.
Documents for payment
Document Submitted by
Contract copySystem generated
Invoice or GST invoiceSeller, uploaded on GeM
Delivery challan, proof of delivery, PRC, CRAC or SDACConsignee, system generated
Customs or excise documents, for imported or excisable goodsSeller
Confirmation of security deposit, where the contract requires itBuyer, online
Price variation documents, where price variation appliesSeller
Bill cum sanction and claim documents, for PFMSSystem generated

For contracts from bids and reverse auctions, payment falls due only after the buyer receives and verifies your performance security, so submit it within 15 days of award.

Penal interest of 1% a month for late payment

The PFMS payment guide says: if payment is not made within 10 days from the CRAC generation date, "the buyer organisation must pay penal interest at the rate of 1% per month for any delay beyond the 10 day period". Interest is calculated pro rata on the actual number of days of delay, and buyers can now pay these interest charges through the PFMS payment method on GeM.

For example, on a bill of ₹5 lakh paid 40 days after the CRAC, the delay beyond 10 days is 30 days, so the interest is about ₹5,000.

Payment methods by buyer type

How different buyers pay on GeM
Payment method Used by
PFMSCentral government ministries
IFMSState government departments
CGDADefence organisations
GeM Pool AccountOrganisations not using PFMS, with challan and non-challan models
Railway payment systemIndian Railways
SBI MOPS internet bankingPayment gateway
ERP integrationVarious central public sector enterprises
OthersOffline NEFT, RTGS or cheque

The methods are listed in the GeM overview of January 2026. The buyer's primary user chooses the method and can change it.

PFMS flow: buyer, DDO, PFMS

  1. Before the contract is generated, the buyer blocks funds against the demand, entering the DDO code and, for e-bills, the programme division code.
  2. After the CRAC, the buyer drafts the bill from the dashboard.
  3. The draft bill goes to the Drawing and Disbursing Officer's account on GeM.
  4. The DDO finalises the bill and pushes it to PFMS through GeM.
  5. Once PFMS pays, the status updates automatically on GeM.

For the PFMS mode, the primary user must register the DDO as the payment authority.

Deductions on bills

The buyer or DDO can apply deductions to a bill, and more than one deduction can apply on a single bill. The PFMS guide sets the limits:

Maximum deductions on a GeM bill
Deduction Limit
Liquidated damages, products0.5% a week, up to 10% of order value
Income-tax TDS1%, 2%, 5% or 10%
GST TDSUp to 2%, on orders of ₹2,50,000 or more
Other deductionsUp to 35%
Product non-deliveryUp to 50%
Service SLA deductionsUp to 10%
Service non-deliveryUp to 99.5%

Liquidated damages are normally capped at 5% of contract value under clause 15 of the GTC; the 10% limit applies to inordinate delay of more than a quarter of the completion period. For example, one week's delay on ₹4 lakh of goods costs ₹2,000 in liquidated damages.

Red and Orange buyer flags

GeM classifies individual buyers by their record of overdue payments:

  • Red: more than 30 payments due for more than 70 days after CRAC.
  • Orange: more than 20 payments due for more than 70 days after CRAC.

According to the January 2026 overview, the flags help sellers make informed decisions, and sellers are not penalised for rejecting orders from Red buyers.

If payment is late: what sellers can do

  1. Check the status on your dashboard. Confirm that the CRAC has been issued and your invoice submitted. The 10-day clock starts only then.
  2. Contact the buyer and the paying authority. Their contact details are on the contract.
  3. Raise a ticket with GeM. Give the order number, CRAC date and bill number, through the GeM support desk. Escalate if it is not resolved within 3 days.
  4. Use the contract's dispute route. The GTC requires an attempt at amicable settlement; if that fails within 30 days of written notice, a Dispute Resolution Committee chaired by the buyer's primary user has 30 days, and after that the Department of Expenditure's arbitration and mediation guidelines of 3 June 2024 apply.
  5. Plan working capital. For future orders, GeM Sahay offers loans against purchase orders, and GeM is integrated with the TReDS invoice-discounting exchanges.

GeM is not a party to the contract and does not pay sellers itself, so it cannot release money on the buyer's behalf.

Frequently asked questions

How many days does GeM take to pay?

The buyer must pay 100% within 10 days of the CRAC (or SDAC for services) and your online bill.

What is CRAC in GeM?

Consignee Receipt cum Acceptance Certificate, issued by the consignee after inspection. It is the basis for payment.

How long does the buyer have to accept goods?

10 days from receipt, as recorded in the PRC, unless the bid or product terms say otherwise.

Is interest paid on late GeM payments?

For PFMS payments, the buyer organisation owes penal interest of 1% a month, pro rata, for delay beyond 10 days from the CRAC.

What is a Red buyer on GeM?

A buyer with more than 30 payments overdue by more than 70 days after CRAC. Sellers are not penalised for rejecting their orders.

What deductions can be made from my bill?

Liquidated damages, TDS, GST TDS and other contract deductions, each within the limits GeM sets.