Independent site, not affiliated with GeM or the Government. Register, bid and pay only on gem.gov.in.
gemportal.in.net हिं
Two men in ordinary work shirts load unmarked brown cartons onto the open back of a small pickup truck with a blank number plate at a warehouse loading bay under an overcast sky; more unlabelled cartons sit on a pallet to the right.

GeM direct purchase limit and every buying mode, by value

The GeM direct purchase limit is ₹50,000. Up to that amount, a government buyer can order from any seller on GeM that meets the quality, specification and delivery period it needs. Over ₹50,000 and up to ₹10 lakh, the buyer must use L1 buying, choosing the lowest price among at least three manufacturers. Over ₹10 lakh, a bid or reverse auction is mandatory.

These limits come from Rule 149 of the General Financial Rules, 2017, as amended by the Department of Expenditure's office memorandum F.1/3/2024-PPD of 10 July 2024. GeM restates them in clause 4 of its General Terms and Conditions, version 1.29.

The three value bands in Rule 149

GeM buying modes by value of the requirement
Value Mode Rule 149 wording in short
Up to ₹50,000Direct purchaseThrough any available supplier meeting quality, specification and delivery period
Over ₹50,000 and up to ₹10 lakhL1 buyingFrom the seller with the lowest price among available sellers of at least three different manufacturers
Over ₹10 lakhBid or reverse auctionFrom the lowest-priced supplier after mandatorily obtaining bids through GeM's online bidding or reverse auction

In all three bands, the procuring authority must certify that the rates are reasonable. Automobiles are an exception in the first band: the note to Rule 149(i) permits their direct purchase "without any ceiling limit".

The bid and reverse auction tools can also be used for values under ₹10 lakh. The 10 July 2024 amendment says so expressly, and clause 4 of the GTC goes further: bidding "should be considered as the preferred mode of procurement above ₹50,000".

What changed on 10 July 2024

The Department of Expenditure doubled both thresholds.

Rule 149 limits before and after 10 July 2024
Mode Until 9 July 2024 From 10 July 2024
Direct purchaseUp to ₹25,000Up to ₹50,000
L1 buyingOver ₹25,000 and up to ₹5 lakhOver ₹50,000 and up to ₹10 lakh
Bid or reverse auction mandatoryOver ₹5 lakhOver ₹10 lakh

The same office memorandum raised the limits for purchases made outside GeM. Purchase without quotation under Rule 154 went up from ₹25,000 to ₹50,000, and purchase by a local purchase committee under Rule 155 now covers ₹50,000 to ₹5 lakh, where it earlier covered ₹25,000 to ₹2.5 lakh. Some websites still quote a direct purchase limit of ₹1 lakh; no such limit exists in Rule 149.

Purchase-mode finder

Enter the estimated value of the whole requirement and answer three questions: is it an automobile, does the buyer hold a Proprietary Article Certificate approved by its competent authority, and is the item or service available on GeM. The finder returns the buying mode Rule 149 allows, the rule that applies, whether bid security and performance security are needed, and whether push button procurement is available. Amounts can be typed as ₹75,000, 8 lakh or 1.2 crore.

The finder applies the central rules. State government buyers should check their own state's procurement rules, which can differ.

Purchase-mode finder

Amounts, counts and yes or no answers only. No GeM ID, PAN, GSTIN, bank detail or login is asked for, and nothing is sent.

For example 8 lakh or 75,000

Direct purchase up to ₹50,000

Direct purchase is the quickest mode. The buyer searches the catalogue, selects a product that meets its need and places the order. The seller's live listing counts as acceptance, so no confirmation is needed from the seller.

Three conditions apply under clause 4 of the GTC:

  • The buyer certifies that the rate is reasonable.
  • The buyer has the approval of its competent authority.
  • If the buyer does not choose the lowest-priced product, it records the reasons for selecting the specific product.

During the carting period, the price of the carted quantity is frozen against any increase by the seller, while any price cut passes to the buyer automatically.

L1 buying from ₹50,001 to ₹10 lakh

In L1 buying, the buyer compares products that meet its requirement and orders from the lowest-priced seller. The GTC says the comparison must cover products of at least three different manufacturers or OEMs. If the buyer wants a specific OEM's product, it must use PAC buying instead.

To decide whether the L1 price is reasonable, buyers can use GeM's business analytics: the last purchase price on GeM, the department's own last purchase price, prices on other e-commerce sites, and the discount over MRP. If the GeM price looks too high, the buyer can run a bid or reverse auction instead. In bids, an eligible MSE within 15% of a non-MSE L1 price can match it and supply up to 25% of the tender.

Push button procurement up to ₹5 lakh

Push button procurement lets a buyer select a pre-defined product and place an order "with just a few clicks", in the words of the GeM overview of January 2026, because price discovery, seller selection and compliance checks are done by the system. It is available up to ₹5 lakh. No performance security is needed, under clause 7 of the GTC.

Bid and reverse auction over ₹10 lakh

Over ₹10 lakh, the buyer must run a bid or a reverse auction, or a bid followed by a reverse auction. The bid is published on GeM with at least 10 clear days before the last date for submission, and invitations go to all sellers listed in the category. Sellers' offers stay valid for 15 days from bid opening, or 30 days from the start of the reverse auction. A bidder who withdraws within the validity period or gives false information loses the bid security.

PAC, custom bids, BoQ bids and rate contracts

  • PAC buying. With a Proprietary Article Certificate approved under Rule 166 of GFR 2017, a buyer can use the PAC filter to buy a specific make or model. The GTC asks for extra care over price, because the OEM controls the price even if several authorised sellers list the product. Over ₹50,000, bidding is still mandatory, and the PAC decision is taken after bidding.
  • Custom bids. For specialised products and services not available on GeM, the buyer gives an undertaking that the need cannot be met from existing catalogues. A custom catalogue bid runs for a minimum of 21 days and a maximum of 45 days.
  • BoQ bids. For composite requirements with many line items, sellers quote item-wise prices against a standard bill of quantities. The total evaluated cost decides the L1 bidder. The GeM overview warns against creating BoQ bids for single items.
  • Demand aggregation and rate contracts. Requirements of many buyers are pooled to get better prices. Rate contract orders carry a transaction charge of 0.30%, capped at ₹3 lakh.

Where only one offer is available in a category, or only one seller remains after a filtered search, the GTC says the buyer should not select that offer. The exception is PAC procurement.

Splitting a demand is not allowed

Clause 4 of the GTC strictly prohibits splitting a demand by creating several bids or reverse auctions for the same goods or services, or by repeated direct or L1 purchases of the same item. Splitting avoids competition and the need for sanction from a higher authority based on the total value of the demand, and violates Rule 149(viii) of the General Financial Rules. GeM can block such bids and cancel such contracts, and the buyer, including its primary user, is held responsible.

In practice, choose the mode on the estimated value of the total demand, the figure the GTC uses for deciding which sanction is needed, not on the value of one delivery or one instalment.

Worked examples

Which mode applies: five examples under the central rules
Requirement Estimated value Mode
Printer cartridges for one office₹38,000Direct purchase from any qualifying seller
Office chairs₹2,40,000L1 buying among at least three manufacturers, or push button procurement if offered
Laptops for a training centre₹9,50,000L1 buying, or a bid if the buyer prefers
Annual housekeeping service₹18,00,000Bid or reverse auction, mandatory
A staff car₹12,00,000Direct purchase allowed, as automobiles have no ceiling

If the office chairs were split into five orders of ₹48,000 so that each could be a direct purchase, that would be splitting a demand, which the GTC prohibits.

Security deposits by mode

Bid security and performance security by buying mode
Mode Bid security (EMD) Performance security
Direct purchaseNoneNone
L1 buyingNoneNone
Push button procurementNoneNone
Bid or reverse auction, estimated value under ₹5 lakhNoneUp to 5% of contract value
Bid or reverse auction, estimated value over ₹5 lakh0.5% to 5% as set by the buyer, 1% recommendedUp to 5% of contract value

The GTC sets the performance security at up to 5% of contract value, noting that the General Financial Rules put it between 3% and 5%. It is submitted within 15 days of award and stays valid for 2 months beyond all contract obligations, including warranty. Eligible MSEs, DPIIT-recognised startups and some other sellers are exempt from bid security, including KVIC, the Coir Board, TRIFED and holders of a valid BIS licence.

Frequently asked questions

What is the direct purchase limit on GeM?

₹50,000, from 10 July 2024. It was ₹25,000 before that.

What is the L1 limit on GeM?

L1 buying applies over ₹50,000 and up to ₹10 lakh. Over ₹10 lakh, a bid or reverse auction is mandatory.

Is the direct purchase limit ₹1 lakh?

No. Rule 149 sets ₹50,000. A figure of ₹1 lakh does not appear in the rule.

Can automobiles be bought by direct purchase over ₹50,000?

Yes. The note to Rule 149(i) allows direct purchase of automobiles without any ceiling.

Can a buyer use a bid for a purchase under ₹10 lakh?

Yes. The bidding and reverse auction tools can be used for any value, and the GTC calls bidding the preferred mode for purchases over ₹50,000.

Is there EMD for bids under ₹5 lakh?

No. Bid security does not apply to bids with an estimated value under ₹5 lakh.

Do these limits apply to state governments?

Rule 149 binds central ministries and departments. States follow their own procurement rules, which may set different limits.